The dismantling of the historic Elphinstone Road Over Bridge (ROB), a century-old structure built in 1913 during the British era, began on Friday as part of a broader infrastructure overhaul linked to the ambitious Sewri -Worli Elevated Connector project of MMRDA. The estimated cost of this Double Decker Bridge is Rs. 168 crore.
The completion period of the Railway portion is around 1 year after dismantling of existing ROB. According to sources, authorities are targeting to complete the dismantling and reconstruction work in two years.
Originally slated for completion within 20 days, the schedule has now been extended until July 10, 2025, due to constraints around railway traffic blocks. The dismantling of the approach roads — excluding the section directly above railway tracks — is expected to conclude by May 30, 2025.
This phase alone involves the removal of around 16,316 cubic meters of solid structures using heavy equipment, including two Poclain.
You may also like
Defence Minister Rajnath Singh meets with Prime Minister Narendra Modi
ED conducts search and seizure actions at 11 premises belonging to different liquor contractors
VIDEO: Ujjain RPF Officials Rescues Woman From Rail Tracks After She Slips While De-boarding Moving Train
Tamil Nadu CM announces 9 welfare measures for State Government employees
India bans 16 Pak YouTube channels for misleading content on Indian Army